November 19, 2026
Bird Key Park is still closed this Thanksgiving. It sits at the base of the John Ringling Causeway Bridge, and it has been closed since the city's October 18, 2024 notice, which cited significant safety hazards after Milton. In late October, Suncoast Searchlight ran a fact brief headlined with the question it keeps hearing, whether the park has reopened. Its answer was no.
The other side of Bird Key Drive is busy. FDOT crews spent this month installing traffic signal mast arms at the Bird Key Drive intersection, building a shared-use path on Bird Key and doing drainage work at the same corner. The two projects sit next to each other and are paid for differently. That explains why the road into Bird Key is scheduled to be finished about a year before the park beside it.
The causeway work is FDOT project 445926-2, a $12.3 million job covering S.R. 789 from east of Sunset Drive to Bird Key Drive. Its scope includes dedicated bicycle and transit lanes on the bridge, drainage upgrades, a raised seawall cap near Sunset Drive, resurfacing, and new traffic signals at Sunset Drive, Golden Gate Drive and Bird Key Drive. Palm trees and shrubs from the eastern end of the causeway are being moved to medians closer to St. Armands Circle. The City of Sarasota announced a January 5, 2026 start, cut the speed limit to 35 mph for the length of construction, and gave an expected finish of early 2027. FDOT's weekly report dated November 12 still shows early 2027.
The park is a city repair, and the city is waiting on federal money. On the City of Sarasota's hurricane recovery page, Bird Key Park has an approved permit. Its status reads "Pre-Construction," with the start "delayed while awaiting FEMA obligation of project funding." Construction is expected to begin in early 2027 and finish in early 2028. Suncoast Searchlight also pointed to the slow FEMA reimbursement process as a reason the repair has taken this long.
The February federal shutdown made the wait longer. Your Observer reported on February 28 that the interim city manager had paused the city's waterfront park repairs, about $10.2 million in work across several parks. Continuing without FEMA authorization could have cost the city its eligibility for reimbursement. Deputy City Manager Patrick Robinson told commissioners that once the projects were demobilized, restarting could take as long as five months. In an April 30 story, Your Observer listed the estimate for Bird Key Park's repairs at $2,254,200. That was the largest figure on the paper's list of remaining city park repairs, though it was still an estimate and not a bid. Only the $3.3 million contract approved for Ken Thompson Park on City Island was bigger.
FDOT has a funded road project with a contractor already working. The city has a permitted park repair it can't start without risking the reimbursement.
FDOT's most recent RoadWatch report, for the week of November 15 to 21, lists the shared-use path on Bird Key, the drainage at Bird Key Drive, and signal wiring and mast arms at Bird Key Drive and Sunset Drive. Milling and paving will resume later. The bike lanes are closed, and cyclists are directed to a posted detour. Pedestrians are told to use designated paths and posted detours. No lane closures were scheduled for that week. Most of the work happens in daytime, with some at night.
At the mainland end of the bridge, walking and bike traffic has moved to the north side of Gulfstream Avenue east of the Sunset Drive and Golden Gate intersection, according to the Coalition of City Neighborhood Associations' project page. On foot or by bike, a loop from Bird Key over the bridge to Bayfront and back runs through detours at both ends right now. FDOT has a project page with a factsheet and a communications contact for questions about a specific crossing.
Both of December's big causeway-area events take place away from the closed park, one at each end of the bridge.
To the west, the City of Sarasota lists Holiday Night of Lights on St. Armands Circle for Friday, December 4, from 4:30 to 9 p.m. The free evening includes the lighting of a 60-foot tree, caroling and a Santa parade. The St. Armands Circle Association's event page gives the evening's schedule as 5:30 to 8 p.m. From Bird Key, the Circle is a short trip west along the stretch where FDOT is moving the causeway palms. For residents of St. Armands, it's a walk.
To the east, the Holiday Boat Parade of Lights runs Saturday, December 12, from 6 to 8 p.m. Visit Sarasota County lists the route as City Island on Lido Key to Bayfront Park. Suncoast Charities for Children, the organizer, says the parade is free and names Bayfront Park and Marina Jack as places to watch, with Marina Jack also suggested for dinner. Bayfront Park has storm repairs of its own on the city's list. Its construction is paused pending FEMA funding, with work expected to resume in late 2026 or early 2027 and finish in early 2027.
The city's park directory describes Bird Key Park as a spot for fishing, biking, watching the sunset, launching a canoe or kayak, and walking a leashed pet, with parking and a walking path. With the park closed since October 2024 and its repairs scheduled into early 2028, Bird Key is without the paddle launch and parking lot at the foot of the bridge for the stretch in between.
For paddlers, Sarasota County's Ted Sperling Nature Park at South Lido has a canoe and kayak launch used by kayakers and paddleboarders. It's open 6 a.m. to 10 p.m., and motorized vessels can't launch there. If you're coming from Bird Key, the Lido Key side of the causeway is now the nearest county option.
For anything with a motor, the city's directory lists Centennial Park at 1059 N. Tamiami Trail with three double-lane boat ramps, kayak and canoe launching, and fishing. The boat-ramp lot there is paid parking. Ken Thompson Park on City Island has a boat ramp and kayak launching in the city's listings. It's also on the city's storm-repair schedule, with completion expected in early 2028.
Hart's Landing is no longer a backup for bait or the dock. The city razed the storm-damaged site on November 10, 2025, and says it intends to restore the docks and rebuild the bait shop.
FDOT is aiming to finish the causeway in early 2027, which is also when the city expects to begin Bird Key Park's repair. If both dates hold, the new signal at Bird Key Drive, the shared-use path on Bird Key and the bike lanes on the bridge will be done as the park's construction crews arrive next door. In the city's schedule, the park construction runs to early 2028.
The Ringling Bridge Run is set for Sunday, April 25, 2027, a few months after FDOT's target for finishing the causeway. Across the water on Lido, recovery has also moved one project at a time, as we covered in our fall update on Lido Beach's sand and the casino pool.
The city's recovery page is the place to watch for Bird Key Park. Once FEMA obligates the funding, the status line there will change from "Pre-Construction." Until then, the city's schedule has construction finishing in early 2028.